Tender sections for construction and
supervision of Sutong Bridge project
Project
Tender
sections for supervison
Tender
sections for construction
Scope and contents
North
link
AJ
A1
Highway subgrade and bridges of K0+3.249~K5+560.0, incl. Tongqi Canal Bridge, Zhuhang Interchange and etc. The road is about 5560 m long.
A2
Highway subgrade and bridges of K5+560.0~K11+0, incl. The service area, the toll plaza and etc. The road is about 5440 m long.
A3
Highway subgrade and bridges of K11+0~K15+041.730. The road is about 4042 m long.
A4
Pavement of the north link
BJ
B1
Superstructures and substructures of the approach from abutment to pier #47. The length is about 2070m
   
B2
Superstructures of the approach from pier #47 to pier #67 and substructures of the approach from pier #48 to pier #66. The length is about 1475m long.
   
B3
Deck pavement
 
CJ
C1
Foundation of north tower(pier #70)and foundations and shafts of auxiliary piers and intermediate piers(piers #67, #68 and #69)
C2
Foundation of south tower(pier #71)and foundations and shafts of auxiliary piers and intermediate piers(piers #72, #73 and #74)
C3
Erection of the body of tower (pier # 70、#71) and the superstructures
C5
Manufacture of steel box girders for the north section, about 1044m long
C6
Manufacture of steel box girders for the south section, about 1044m long
C7
Manufacture of stayed-cables
C8
Manufacture of bearings for the main bridge
C9
Construction of impact-preventing facilities
C10
Manufacture of expansion joints for the main bridge
C11
Steel deck pavement
 
DJ
D1
Superstructures of pier #74 to #82, substructures of piers #75 to #81, about 923m long


D2
Superstructures and substructures of pier #82 to #115, about 1650m long
D3
Deck pavement
South
link
FJ
F1
Highway subgrade and bridges of K23+587.0~K26+320, incl. the interchange at Changshu Port. The road is about 2733 m long.
F2
Highway subgrade and bridges of K26+320~K32+765.77 . The road is about 6446 m long.
F3
Pavement of the south link
Others
GJ
G
Traffic works(including three major systems, toll facilities, electromechanical works and safety facilities)
HJ
H
Auxiliary works (including buildings, short pieces, greenings, lightings, paintings and etc.)